BESS Commissioning Checklist: Key Tests Before Energisation

Battery Energy Storage Systems, commonly known as BESS, are becoming an important part of modern power infrastructure. Utility-scale battery storage projects support renewable energy integration, grid stability, and flexible power management.
However, construction completion does not mean that a BESS facility is ready for operation. Before energisation, the battery system, electrical infrastructure, protection equipment, control systems, communications, and safety systems must be inspected and tested. These systems may function individually, but commissioning must confirm that they are ready to operate safely as part of an integrated facility.
A structured BESS commissioning checklist helps project teams identify problems before electrical energy is introduced into the system. It also improves coordination between project owners, EPC contractors, equipment manufacturers, commissioning engineers, protection specialists, and control system teams. This guide covers the key tests and verification activities that should be completed before BESS energisation.
What Is BESS Commissioning?
BESS commissioning is the structured process of inspecting, testing, and verifying a battery energy storage facility before it enters normal operation. The process confirms that:
- Equipment has been installed correctly
- Electrical systems are ready for energisation
- Protection systems operate correctly
- Control systems respond as intended
- Communication networks function properly
- Safety systems are operational
- Different systems can work together as an integrated facility
Commissioning normally begins before final energisation and continues through functional testing and system integration. The exact requirements depend on the BESS design, installed equipment, project size, grid interconnection requirements, and manufacturer specifications.
Need Engineering Support for Your Power Project?
American Power Engineers delivers power system studies, substation design, renewable energy engineering, BESS projects, NERC compliance, MEP engineering, and POI interconnection services.
Explore Our Engineering ServicesWhy Is BESS Commissioning Important?
A BESS facility contains multiple systems that must interact correctly. These can include battery racks, Battery Management Systems, Power Conversion Systems, transformers, switchgear, protection relays, plant controllers, SCADA platforms, and communication networks. Problems are often not visible until systems begin interacting.
For example, a Power Conversion System may operate correctly in local mode but fail to respond to commands from the plant controller. A protection relay may contain the correct settings but have a wiring problem affecting the trip circuit. Similarly, a Battery Management System may function correctly while communication with the wider control system remains incomplete.
A structured commissioning process helps identify these problems before they affect energisation or commercial operation. It also helps ensure that testing follows the correct sequence.
1. Confirm Construction Completion and System Readiness
Before electrical commissioning begins, the relevant equipment must be physically installed and ready for testing. The commissioning team may inspect:
- Battery containers or enclosures
- Battery racks
- Power Conversion Systems
- Transformers
- Medium-voltage equipment
- Switchgear
- Protection and control panels
- AC and DC cabling
- Grounding systems
- Communication infrastructure
- Auxiliary power systems
Physical installation alone does not mean that the equipment is ready for energisation. However, incomplete construction can prevent effective commissioning and create unnecessary delays. Project teams should clearly define system boundaries and identify what work must be completed before each commissioning activity begins.
Review Outstanding Issues
Any incomplete work should be recorded through a structured punch list process. Critical issues affecting safety, electrical integrity, protection, or energisation readiness should be resolved before the affected equipment is energised. Common issues may include:
Planning a Solar, Wind, BESS, or Grid Interconnection Project?
Our engineering team helps project owners, developers, utilities, and facility teams move from technical planning to reliable project execution.
View Engineering Services- Incorrect cable terminations
- Damaged equipment
- Incomplete grounding
- Missing equipment labels
- Incomplete protection wiring
- Communication failures
- Unfinished safety systems
A clear issue management process helps prevent unresolved problems from moving into later commissioning stages.
2. Verify Electrical Drawings and Documentation
Accurate documentation is essential during commissioning. Engineers need to understand how the facility was designed and how the installed systems are expected to operate. Important documentation may include:
- Single-line diagrams
- Electrical schematics
- Protection and control drawings
- Cable schedules
- Equipment datasheets
- Protection settings
- Control philosophies
- Communication architecture drawings
- Approved test procedures
- Manufacturer manuals
Outdated drawings can cause significant problems.
For example, field modifications may have changed an electrical connection while the commissioning team is working from an earlier version of the drawings. This can lead to testing delays and troubleshooting difficulties.
Before energisation, the project team should confirm that the required documentation is available and reflects the current installation.
3. Inspect Battery Systems and DC Infrastructure

The battery system itself must be inspected before electrical energisation. Depending on the technology and project design, verification may include:
- Battery rack installation
- Mechanical condition
- Module and enclosure verification
- Battery Management System connections
- DC cable inspections
- Connector checks
- Equipment labelling
- Required access and clearances
The commissioning team should verify that the battery equipment has been installed according to the approved project documentation and manufacturer requirements.
DC Electrical Testing
The DC side requires careful verification before it is placed into service. Depending on the system design and manufacturer requirements, testing may include:
- Cable continuity testing
- Polarity verification
- Connection checks
- Grounding verification
- DC circuit inspections
- Battery Management System verification
Incorrect polarity or connection problems can create serious issues during energisation. Testing procedures should always follow the requirements of the installed battery technology and equipment.
4. Verify AC Electrical Infrastructure
The AC electrical infrastructure connects the battery storage facility to the wider power system. Before energisation, engineers may inspect and test:
- Power Conversion Systems
- Transformers
- Medium-voltage cables
- Switchgear
- Circuit breakers
- Auxiliary transformers
- Bus systems
Typical testing activities may include:
- Cable continuity checks
- Insulation testing
- Transformer testing
- Circuit breaker operational checks
- Switchgear inspections
- Phase identification
- Control circuit verification
The purpose is to identify installation, wiring, or configuration issues before operational voltage is introduced. For facilities connected through complex high-voltage infrastructure, the readiness of the wider electrical system must also be considered before energisation. This can include reviewing the equipment and interfaces associated with substation design engineering before the facility is energised.
5. Verify Grounding and Earthing Systems
Proper grounding is essential for electrical safety and equipment protection. Before energisation, the relevant grounding systems should be inspected according to project requirements. Verification may include:
- Equipment grounding connections
- Grounding conductors
- Bonding connections
- Ground grid interfaces
- Continuity of grounding paths
For larger BESS facilities connected through substations, grounding design and verification can be a significant part of commissioning readiness. A grounding system should not simply be assumed to be complete because the equipment has been physically installed.
6. Complete Protection and Relay Testing
Protection systems are among the most important systems to verify before energisation. Their purpose is to detect abnormal electrical conditions and initiate the appropriate response to protect equipment and support safe operation. Commissioning activities may include:
- Protection settings verification
- Relay configuration checks
- Secondary injection testing
- CT and VT circuit verification
- Trip circuit testing
- Circuit breaker interface testing
- Protection logic verification
- Communication testing
- Interlock verification
The objective is not simply to confirm that an individual relay operates. Protection performance is also closely connected to the results of power system studies, which can help engineers evaluate system conditions, equipment performance, and protection requirements before a facility enters operation. Incorrect settings, wiring errors, or coordination problems can lead to unnecessary trips or prevent equipment from responding correctly during abnormal conditions.
7. Test the Power Conversion System
The Power Conversion System, or PCS, converts electrical energy between the DC battery system and the AC power network. Before energisation, the commissioning team should verify that the PCS installation, controls, and interfaces are ready for operation. Testing may include:
- Configuration verification
- Local control checks
- Remote control interface testing
- Alarm verification
- Interlock testing
- Communication checks
- Status signal verification
The PCS must communicate correctly with the Battery Management System and the higher-level plant control system. A system may operate correctly in local mode while experiencing problems when it receives commands remotely. For this reason, end-to-end testing is important before the facility moves into full operation.
8. Verify BMS, SCADA, and Communication Systems

The Battery Management System monitors and manages battery operation. Before energisation, engineers should verify that communication paths are functioning correctly between the different systems.
Testing may include:
- Device communication checks
- Status verification
- Alarm signal testing
- Measurement verification
- Communication between battery components
- Communication between the BMS and PCS
- Communication with plant controls
SCADA commissioning should also verify that information moves correctly between field equipment and the operational control platform. Effective commissioning and system integration are particularly important in complex power systems engineering projects where multiple electrical and control systems must operate together.
Important checks can include:
- Point-to-point testing
- Status signal verification
- Measurement checks
- Alarm testing
- Command testing
- Communication protocol verification
- Network connectivity checks
A device appearing online does not necessarily mean that the complete system is functioning correctly. Engineers should verify the complete control sequence. A command should reach the correct equipment, produce the intended response, and return accurate status information to the control system.
9. Verify Plant Controller Functions
The plant controller coordinates BESS operation at the facility level. Before full energisation and operational testing, the project team should confirm that relevant control functions are configured correctly. These control functions must also support the facility’s wider connection requirements. Proper coordination during grid interconnection engineering can help ensure that plant controls and operating parameters align with the requirements of the connected power system. Depending on project requirements, these may include:
- Active power control
- Reactive power control
- Voltage control
- Frequency response
- Charging and discharging commands
- Operating limits
- Equipment availability signals
Control settings should align with the approved engineering design and applicable grid requirements. Problems discovered late in commissioning can require configuration changes and repeat testing. Early verification can help reduce delays.
10. Confirm Safety and Emergency Systems
Safety verification is an essential part of BESS commissioning. Depending on the project and battery technology, systems requiring verification may include:
- Emergency shutdown systems
- Fire detection systems
- Fire suppression interfaces
- Ventilation systems
- Thermal management systems
- Alarm systems
- Emergency communication procedures
The exact scope depends on the facility design and applicable requirements. Safety-related systems and their interfaces should be tested according to approved procedures before the facility enters operation.
11. Conduct an Energisation Readiness Review
Before energisation, the project team should conduct a formal readiness review. This review brings together the results of the different commissioning activities and confirms whether the relevant systems are ready to proceed.
The review may consider:
- Construction completion status
- Electrical test results
- Battery system readiness
- Protection test results
- SCADA and communication readiness
- Control system verification
- Safety system status
- Critical punch list items
- Approved energisation procedures
- Required approvals
The purpose is to ensure that energisation does not proceed based on assumptions or incomplete information. All relevant stakeholders should understand the energisation sequence and their responsibilities.
Practical Pre-Energisation BESS commissioning checklist
Before proceeding with energisation, confirm the following:
Construction and Documentation
- Relevant construction work is complete
- Critical punch list items are closed
- Current drawings are available
- Equipment documentation has been reviewed
- Approved commissioning procedures are available
Battery and Electrical Systems
- Battery equipment has been inspected
- DC connections have been verified
- AC electrical testing has been completed
- Transformers and switchgear have been inspected
- Grounding systems have been verified
- Control circuits have been tested
Protection and Control
- Protection settings have been verified
- Relay testing has been completed
- CT and VT circuits have been checked
- Trip circuits have been tested
- Relevant interlocks have been verified
- PCS controls have been checked
Communication and Safety
- BMS communication has been verified
- SCADA points have been checked
- Communication links have been tested
- Commands and status signals have been verified
- Plant controller functions have been reviewed
- Relevant safety systems have been tested
Final Readiness
- The energisation sequence is approved
- Responsible personnel are identified
- Emergency procedures are available
- Required approvals have been obtained
Common Problems Found Before BESS Energisation
Commissioning is designed to identify problems before they affect normal operation. Some common issues include:
- Communication and Data Problems: Network configuration errors, missing connections, protocol mismatches, or incorrect data mapping can affect monitoring, alarms, and control functions. These issues may only become visible when different BESS systems begin operating together.
- Protection Configuration Issues: Problems can result from incorrect relay settings, wiring errors, incorrect CT or VT configurations, or issues within trip circuits. Because protection systems are closely connected to the wider electrical infrastructure, resolving these issues may require coordination between multiple engineering disciplines.
- Incomplete or Outdated Documentation: Construction changes do not always get reflected immediately in drawings or technical records. When documentation does not accurately represent the installed system, troubleshooting becomes more difficult and commissioning activities may take longer.
- Interface Problems Between Systems: A BESS project often includes equipment from different suppliers. Each system may function correctly on its own but experience problems when integrated with the BMS, PCS, plant controller, or SCADA platform.
What Happens After BESS Energisation?
Energisation is an important milestone, but it is not the end of commissioning. After the facility is energised, engineers continue with functional and integrated testing. This may include:
- Charging and discharging tests
- Active power response testing
- Reactive power testing
- Plant controller testing
- SCADA command verification
- Protection response testing
- Grid-related performance testing
The purpose is to confirm how the facility performs under operating conditions. Some problems only become visible when the complete BESS operates as an integrated system.
Need Support with BESS Commissioning?
BESS commissioning requires careful coordination between battery systems, power conversion equipment, electrical infrastructure, protection systems, SCADA platforms, plant controls, and grid interconnection requirements. Grid Engineering Group supports complex power and renewable energy projects through specialist battery storage engineering, power system analysis, grid interconnection, and technical advisory services. Our team can help project teams through owner’s technical advisory services, including system readiness assessments, protection and control verification, technical interface management, and preparation for critical energisation milestones.
Whether your BESS project is approaching commissioning or facing technical challenges during testing, early engineering support can help identify issues before they affect the project schedule.
Contact Grid Engineering Group to discuss your BESS commissioning and engineering requirements.
Frequently Asked Questions
What is BESS commissioning?
BESS commissioning is the process of inspecting, testing, and verifying a Battery Energy Storage System before it enters normal operation. It covers battery equipment, electrical systems, protection, controls, communications, and system integration.
What tests are required before BESS energisation?
Common activities include electrical testing, grounding verification, protection and relay testing, PCS checks, BMS communication testing, SCADA verification, control testing, and safety system checks.
What is checked during BESS pre-commissioning?
Pre-commissioning may include equipment inspections, cable and connection checks, electrical testing, grounding verification, control circuit testing, communication checks, and documentation review.
Why is protection testing important before energisation?
Protection testing verifies that relays and associated systems can detect abnormal electrical conditions and initiate the appropriate response. Incorrect settings or wiring can create serious safety and operational risks.
What happens after a BESS is energised?
After energisation, engineers perform functional and integrated testing to verify charging and discharging performance, control response, communication, protection operation, and other project-specific requirements.
How can BESS commissioning delays be reduced?
Early planning, clear responsibilities, accurate documentation, structured punch list management, early interface testing, and coordination between equipment vendors and engineering teams can help reduce delays.